Day 62 – Doors

Spent a couple of days hanging the new internal doors.

Comments off

Day 60 – Overview

I thought it was time for an overview of where we are so far. POSH’s work is finished. All issues have been resolved to our satisfaction and we are very pleased with the results.

The outstanding tasks for me now are:

  1. Hang and paint the interior doors.
  2. Lay a new patio.
  3. Buy furniture and consumer electronics.

Comments off

Day 60 – Carpet

The carpet was fitted today.

Comments off

Day 59 – Painting The Door Frame

In the last couple of days the door frame has had a couple of coats of paint.

Comments off

Day 57 – Keys and Guttering

The locks have been swapped for a matched pair.

All remaining black brackets have now been replaced with white brackets on the guttering.

Comments off

Day 57 – Carpet Cleaning

We had £200 knocked off the bill to pay for the carpet to be cleaned.

Comments off

Day 55 – Door Frame

Added the doorstop to the frame myself. I would have rather done this after installing the doors but it needed doing to define the door location for the carpet fitters. There was no way I would get the doors and the doorstop fitted before Friday. This also allows me to paint it before the carpet is fitted.

After painting, my next major job will be to install these.

Comments off

Day 53 – Guttering and Floor

The guttering was changed to white. There is still a couple of black brackets as POSH were out of stock but these should be changed next week.

And the floor had a final layer of concrete to raise the level to the same as our existing lounge.

Comments off

Day 52 – Door Removal

Had the old patio door removed today.

And the final piece of roof trim was installed.

Comments off

Day 51 – Inspection

The building inspectored sign off the build today.

Comments off

Day 49 – Power On

It’s been a while but finally the power has been connected and we have light.

The next step is for the building inspector to sign-off the build so far. POSH then have to complete the following:

  • Finish trim between ceiling and roof
  • Change guttering to white
  • Remove existing door, fix plaster and skirting (followed by me painting it)
  • Change locks for a matched pair

Hopefully this will be done by Friday 1st August as Downs carpets are booked to lay a new carpet. I’ve then got a busy few weeks (or maybe months) installing new internal doors and laying a new patio.

Comments off

Day 41 – Gloss Paint

Painted the skirting board today.

Comments off

Day 38 – Electrics & Plumbing

The electrician returned for the second fit of lights and power sockets. Unfortunately the power couldn’t be connected up due to an existing issue in our downstairs ring main. More investigation required.

And our plumber fitted a radiator.

Comments off

Day 37 – Guttering

I have spoken to POSH and confirmed we want the guttering replaced with white and it is now on order. POSH are covering the installation costs and we are having to pay for the parts.

Comments off

Day 36 – Walls

The result of two evenings worth of painting with Dulux Buttermilk.

Comments off

Day 34 – Ceiling

Two top coats have been applied to the ceiling. Need to wait for the final piece of trim to cover the lead and the rough edge.

I’ve also undercoated the skirting board.

Comments off

Day 33 – Undercoat

Today, the ceiling and walls had a coat of undercoat. The finish isn’t very exciting, so I thought I would show the workers in action instead.

Comments off

Day 32 – Colours

Picked up some paint samples from B&Q. Ceiling and skirting will be white, but what about the walls? Decisions, decisions…

Comments off

Day 31 – Plaster

Walls are now fully filled and sanded.

Comments off

Day 30 – Skirting

The skirting board is finished.

Additionally, work is continuing on the plaster. Hopefully finished tomorrow.

Comments off

Day 29 – Plaster Repaired

After a call to POSH, they aggreed to come out and fix the finish on the plaster. Everything has been filled but it still needs a sand tomorrow. This picture should highlight how much repairing was required.

Comments off

Day 26 – Plaster

The plaster is done. Should be ready for paint in about 3 days. I don’t know whether POSH are going to sand it or whether we have to first though? (more info)

Once painted we need:

  • Second fit electrics.
  • Plumbing for radiator.
  • Skirting boards.
  • Flooring.

Comments off

Issues

Although we have been very impressed with the efficiency and quality of the service so far, there are always issues that crop up. I’ve added a page to catalogue all of the outstanding issues here.

Comments off

Day 25 – Plaster Board

Walls have been boarded and the ceilling has its first coat of plaster.

Comments off

Day 24 – Plaster Arrives

The plaster has been left for tomorrow.

Comments off

Day 22 – Waiting

I think we are now currently waiting for the building inspector before the plasterer can do his thing.

Comments off

Day 20 – Windows

Previously the windows just had temporary panes of glass in to keep the weather out. The correct double glazzed units with integral blinds have been installed this morning.

We noticed today that the two doors have non-matched locking mechanisms. This might be annoying in the long term having to have two keys on every bunch just for these doors.

Comments off

Day 19 – The Roof

The roof has been installed in a day. It looks very impressive and worth the money.

Comments off

Day 18 – ?????????

Where are the builders? I think we are now waiting for the roof as it needs to be weather proof before any other jobs can be completed. Lets hope they arrive tomorrow.

Comments off

Day 17 – Electrics First Fit

First fit of electrics today.

Comments off

Day 16 – More Work On The Roof

Doesn’t look like much from ground level, but the flat part of the roof is progressing.

Comments off

Day 15 – Window Frames

The window and door frames are in. They currently have temporary glass in until the proper panes arrive. The guttering has also been installed.

We are unconvinced about the black guttering. We were advised to go for black so it blends in with the flat part of the roof but as the rest of the windows and roof are white, as well as our existing windows and guttering, we are unsure this is correct.

Comments off

New Air Brick

Yesterday a new air brick was installed on the side wall of our living room as the existing air brick would be blocked by the new wall. It is our first area of disappointment as they weren’t very neat in cutting a section from the wallpaper and the black dust has stained our carpet.

Comments off

Day 12 – Roof Nearly Finished

The roof is looking nearly finished now (apart from the glass obviously).

Comments off

Day 11 – More Framing

Slow progress today, but then the weather was horrible.


 

Comments off

Day 10 – The Roof Frame

The carpenters have arrived and made a good start.

Comments off

Day 9 – The Concrete Floor

The concrete floor has been poured.

Comments off

Day 8 – A Bit More Brick Work

A few more courses of bricks (with the thinnest lintels I’ve ever seen).

We also have what looks like the underfloor insulation ready to lay.

Comments off

Day 5 – Brick Work Finished (I Think)

The brick work looks finished now.

 

 

Comments off

Day 4 – More Brick Work

The brick work is nearly finished now.

 

Comments off

Day 3 – Brick Work

A start has been made on the brick work.

Comments off

Day 2 – Laying The Foundations

The front of the house has now been cleared. At the rear, the concrete has now been poured and the soak-away has been dug.

Comments off

Day 1 – Digging The Foundations

Coming home from work on the first day and it looks like a lot has been happening.

Around the back of the house and we can see what progress has been made.

Comments off

Salvaging Slabs

Although the builders were supposed to lift the paving slabs and save them, we had little hope in this occuring as the slabs were cemented down. We had a go ourselves as there were some specific slabs we wanted kept.

In progress.

The result.

Comments off

Clearing The Site

Before starting the extension, this was the state our patio was in.

A couple of hours of tidying-up and we were left with this.

Comments off

The Amended Design

The design has to change as the original one had brick pillars between the windows that were too narrow. This is an approximate CAD render although is it slightly flawed as it shows a floating roof.

Comments off

We’ve Done It Now

We’ve paid the deposit.

We know it was probably a sales trick, but there was a discount if we signed before the end of the financial year.

Comments off

The Design

The final design we’ve chosen.

Comments off

Selecting an Extension

After trawlling around several conservatory companies we settled on POSH Windows & Conservatories. Their showroom had an example of the sort of structure we were looking for. It needed a large amount of brick rather than the traditional conservatory which is almost 100% glass. This is because we wanted to use the room all year round and at all hours of the day. Technically this becomes an orangery.

 

Additionally, we liked the salesman and their practice of employing builders instead of contracting them out.

Comments off

Our Lovely Patio

The original patio layed in 2004.

Comments off